Multiple Choice
Using the three-point estimate technique, what is the estimated time to complete a project based on the following scenario?
Kyle has been appointed to draw up a cost estimate for a new project. He interviews one of the engineers, Steve, who tells Kyle his assigned task will take 3 weeks. Upon being questioned, Steve changes his estimated completion time to 7.5 weeks. Kyle thinks a realistic estimate is 4.5 weeks.
A) 3 weeks
B) 4.75 weeks
C) 5 weeks
D) 7.5 weeks
Correct Answer:

Verified
Correct Answer:
Verified