Multiple Choice
Which of the following best describes the scheduling term float?
A) Amount of time spent on a specific task
B) Time to complete a specific task that is dependent on a preceding task
C) Amount of time a task can be delayed without impacting a subsequent task or project completion date
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified