Variance analysis facilitates the principle of "management by exception."
Question 122
Essay
Loomis Company uses both standards and budgets. The company estimates that production for the year will be 250,000 units of Product Fast. To produce these units of Product Fast, the company expects to spend $600,000 for materials and $800,000 for labor. Instructions Compute the estimates for (a) a standard cost and (b) a budgeted cost.
Question 123
True/False
A direct labor price standard is frequently called the direct labor efficiency standard.
Question 124
Multiple Choice
Fugate Company planned to use 1 yard of plastic per unit budgeted at $81 a yard. However, the plastic actually cost $80 per yard. The company actually made 2,600 units, although it had planned to make only 2,200 units. Total yards used for production were 2,640. How much is the total materials variance?
Question 125
True/False
In concept, standards and budgets are essentially the same.
Question 126
True/False
Standard cost + price variance + quantity variance = Budgeted cost.
Question 127
Multiple Choice
Keller Company has a materials price standard of $2.00 per pound. Five thousand pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 5,000 pounds, although the standard quantity allowed for the output was 4,500 pounds. Keller Company's total materials variance is
Question 128
Multiple Choice
A company developed the following per unit materials standards for its product: 3 pounds of direct materials at $4 per pound. If 12,000 units of product were produced last month and 37,500 pounds of direct materials were used, the direct materials quantity variance was
Question 129
Multiple Choice
ToolTime has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of $46,970. ToolTime's labor quantity variance is
Question 130
Multiple Choice
ToolTime has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of $46,970. ToolTime's total labor variance is
Question 131
True/False
A debit to the Overhead Volume Variance account indicates that the standard hours allowed for the output produced was greater than the standard hours at normal capacity.
Question 132
Multiple Choice
ToolTime has a standard of 1.5 pounds of materials per unit, at $4 per pound. In producing 2,000 units, ToolTime used 3,100 pounds of materials at a total cost of $12,090. ToolTime's materials price variance is
Question 133
Multiple Choice
The per-unit standards for direct materials are 2 pounds at $4 per pound. Last month, 11,200 pounds of direct materials that actually cost $42,400 were used to produce 6,000 units of product. The direct materials quantity variance for last month was
Question 134
Multiple Choice
The following information was taken from the annual manufacturing overhead cost budget of Coen Company.
During the year, 5,600 units were produced, 18,340 hours were worked, and the actual manufacturing overhead was $75,600. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis of direct labor hours. Coen's total overhead variance is
Question 135
Multiple Choice
The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1,200 units, the actual direct labor cost was $32,000 for 2,000 direct labor hours worked, the total direct labor variance is
Question 136
Short Answer
A ________________ is expressed as a unit amount, whereas a _________________ is expressed as a total amount.
Question 137
Multiple Choice
The direct materials price standard should include an amount for all of the following except
Question 138
True/False
An unfavorable labor quantity variance indicates that the actual number of direct labor hours worked was greater than the number of direct labor hours that should have been worked for the output attained.