Question 181
Essay
Benton Company produces one product, a putter called PAR-putter. Benton uses a standard cost system and determines that it should take one hour of direct labor to produce one PAR-putter. The normal production capacity for this putter is 100,000 units per year. The total budgeted overhead at normal capacity is $600,000 comprised of $200,000 of variable costs and $400,000 of fixed costs. Benton applies overhead on the basis of direct labor hours. During the current year, Benton produced 85,000 putters, worked 89,000 direct labor hours, and incurred variable overhead costs of $180,000 and fixed overhead costs of $400,000. Instructions (a) Compute the predetermined variable overhead rate and the predetermined fixed overhead rate. (b) Compute the applied overhead for Benton for the year. (c) Compute the total overhead variance.
Question 182
Short Answer
The overhead ______________ variance is the difference between normal capacity hours and standard hours allowed times the fixed overhead rate.
Question 183
Essay
The following direct labor data pertain to the operations of Nagel Manufacturing Company for the month of November:
Instructions Prepare a matrix and calculate the labor variances.
Question 184
Multiple Choice
A company purchases 20,000 pounds of materials. The materials price variance is $3,000 favorable. What is the difference between the standard and actual price paid for the materials?
Question 185
Essay
Manufacturing overhead data for the production of Product B by Elliott Company are as follows.
Instructions Compute the controllable and volume overhead variances.
Question 186
Essay
Landis Company planned to produce 20,000 units of product and work 100,000 direct labor hours in 2011. Manufacturing overhead at the 100,000 direct labor hours level of activity was estimated to be:
At the end of 2011, 21,000 units of product were actually produced and 108,000 actual direct labor hours were worked. Total actual overhead costs for 2011 were $1,025,000. Instructions (a) Compute the total overhead variance. (b) Compute the overhead controllable variance. (c) Compute the overhead volume variance.
Question 187
Essay
Vega Company has developed the following standard costs for its product for 2011:
The company expected to produce 25,000 units of Product A in 2011 and work 75,000 direct labor hours. Actual results for 2011 are as follows:
β
\bullet
β
26,000 units of Product A were produced.
β
\bullet
β
Actual direct labor costs were $630,800 for 76,000 direct labor hours worked.
β
\bullet
β
Actual direct materials purchased and used during the year cost $283,500 for 105,000 pounds.
β
\bullet
β
Actual variable overhead incurred was $130,000 and actual fixed overhead incurred was $170,000. Instructions Compute the following variances showing all computations to support your answers. Indicate whether the variances are favorable or unfavorable. (a) Materials quantity variance. (b) Total direct labor variance. (c) Direct labor quantity variance. (d) Direct materials price variance. (e) Total overhead variance.
Question 188
Multiple Choice
Which of the following statements about standard costs is false?
Question 189
Multiple Choice
Keller Company has a materials price standard of $2.00 per pound. Five thousand pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 5,000 pounds, although the standard quantity allowed for the output was 4,500 pounds. Keller Company's materials price variance is
Question 190
Multiple Choice
An unfavorable materials quantity variance would occur if
Question 191
Multiple Choice
Kitselman Inc. produces a product requiring 3 direct labor hours at $20.00 per hour. During January, 2,000 products are produced using 6,300 direct labor hours. Kitselman's actual payroll during January was $122,850. What is the labor quantity variance?
Question 192
Multiple Choice
If the standard hours allowed are less than the standard hours at normal capacity,
Question 193
True/False
A materials quantity variance is calculated as the difference between the standard direct materials price and the actual direct materials price multiplied by the actual quantity of direct materials used.