Country risk can affect an MNC's cash flows but cannot affect its cost of capital.

(True/False)
4.9/5
(99)

A mild form of political risk is a tendency of residents to purchase only:

(Multiple Choice)
4.9/5
(79)

The primary purpose of country risk analysis when applied to capital budgeting is usually to:

(Multiple Choice)
4.9/5
(78)

The Multilateral Investment Guarantee Agency can provide MNCs implementing direct foreign investment in less developed countries with:

(Multiple Choice)
4.9/5
(86)

Country risk analysis is important because it:

(Multiple Choice)
4.8/5
(90)

Unlike project risk, country risk cannot be incorporated into the capital budgeting analysis of a proposed project by adjustment of the discount rate or by adjustment of the estimated cash flows.

(True/False)
4.9/5
(81)

Since country risk is constantly changing and events in other parts of the world are largely unpredictable, country risk analysis is not important for MNCs.

(True/False)
4.9/5
(81)

A macro-assessment of country risk:

(Multiple Choice)
4.8/5
(86)

Which of the following is not a way in which country risk analysis can be used?

(Multiple Choice)
4.8/5
(76)

____ is not a political risk factor.

(Multiple Choice)
4.9/5
(92)

While an overall risk rating of a country can be useful, it cannot always detect upcoming crises.

(True/False)
4.9/5
(97)

Eurenasia is a country that has frequently been assigned low macro-assessment ratings of country risk in the recent past due to its tendency to war with neighboring nations. MNC A is considering the establishment of a subsidiary to manufacture personal computers, while MNC B is considering the establishment of a subsidiary to manufacture tanks. Which of the two MNCs is likely to be less affected by the low macro-assessment?

(Multiple Choice)
4.8/5
(87)

____ is (are) not a form of political risk.

(Multiple Choice)
4.8/5
(71)

The checklist approach:

(Multiple Choice)
4.8/5
(88)

Risk assessors almost always arrive at the same opinion after completing a macro-assessment of country risk.

(True/False)
4.8/5
(70)

When using a checklist approach to assess country risk, factors should be converted to some numerical forms and assigned equal weights.

(True/False)
4.7/5
(82)

When the war in Iraq began in 2003, some MNCs feared that oil prices would ____ and that U.S. inflation and interest rates would ____.

(Multiple Choice)
4.9/5
(84)