Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B?

(Multiple Choice)
4.8/5
(76)

   -Use the Gantt chart and activity list to determine which resource is used the most.  \begin{array} { | l | l | l | l | }  \hline \text { Activity } & \text { Resources } & \text { Activity } & \text { Resources } \\ \hline \mathbb { R } & 5 & \mathrm { M } & 1 \\ \hline \mathrm { H } & 1 & \mathrm {~K} & 4 \\ \hline \mathrm { G } & 5 & \mathrm {~T} & 3 \\ \hline \mathbb { F } & 2 & \mathrm { P } & 1 \\ \hline \mathrm { B } & 2 & \mathrm {~S} & 2 \\ \hline \mathrm { T } & 4 & \mathrm {~W} & 3 \\ \hline \end{array} -Use the Gantt chart and activity list to determine which resource is used the most. Activity Resources Activity Resources 5 1 1 4 5 3 2 1 2 2 4 3

(Multiple Choice)
4.9/5
(94)

Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days. Activity Duration Predecessor 6 - 3 7 5 10 8 , 6 4 10 5 ,

(Essay)
4.9/5
(83)

Sketch a network and use it as an example as you discuss the four different logical relationships between activities.

(Essay)
4.7/5
(82)

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 35 days? Normal Normal Activity Predecessor Time Cost Crash Time Crash Cost -- 3 \ 12,000 5 \ 22,000 12 \ 18,000 9 \ 32,000 15 \ 22,000 9 \ 62,000 3 \ 9,000 \ 18,000 9 \ 15,000 5 \ 35,000 7 \ 5,000 5 \ 8,000 3 \ 13,000 6 \ 23,000 12 \ 20,000 8 \ 32,000 6 \ 45,000 4 \ 56,000

(Multiple Choice)
4.7/5
(80)

   -Use the Gantt chart and activity list to determine when resource 3 is free.  \begin{array} { | l | l | l | l | }  \hline \text { Activity } & \text { Resources } & \text { Activity } & \text { Resources } \\ \hline \mathbb { R } & 3 & \mathrm { M } & 1 \\ \hline \mathrm { H } & 1 & \mathrm {~K} & 5 \\ \hline \mathrm { G } & 4 & \mathrm {~T} & 3 \\ \hline \mathbb { F } & 2 & \mathrm { P } & 1 \\ \hline \mathrm { B } & 2 & \mathrm {~S} & 2 \\ \hline \mathrm { T } & 4 & \mathrm {~W} & 3 \\ \hline \end{array} -Use the Gantt chart and activity list to determine when resource 3 is free. Activity Resources Activity Resources 3 1 1 5 4 3 2 1 2 2 4 3

(Multiple Choice)
4.8/5
(79)

Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?

(Multiple Choice)
4.8/5
(86)

   -Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.  \begin{array} { | l | l | l | l | }  \hline \text { Activity } & \text { Resources } & \text { Activity } & \text { Resources } \\ \hline \text { A } & 1 & \text { F } & 2 \\ \hline \text { B } & 3 & \text { G } & 3 \\ \hline \text { C } & 4 & H & 4 \\ \hline \text { E } & 2 & \text { I } & 5 \\ \hline \end{array} -Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. Activity Resources Activity Resources A 1 F 2 B 3 G 3 C 4 H 4 E 2 I 5

(Multiple Choice)
4.9/5
(73)

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 40 days? Normal Normal Activity Predecessor Time Cost Crash Time Crash Cost -- 3 \ 12,000 5 \ 22,000 12 \ 18,000 9 \ 32,000 15 \ 22,000 9 \ 62,000 3 \ 9,000 2 \ 18,000 9 \ 15,000 5 \ 35,000 7 \ 5,000 5 \ 8,000 3 \ 13,000 6 \ 23,000 12 \ 20,000 8 \ 32,000 6 \ 45,000 4 \ 56,000

(Multiple Choice)
4.8/5
(75)

An activity on an arrow network:

(Multiple Choice)
4.8/5
(66)

What are the strengths and weaknesses of AOA and AON techniques?

(Essay)
4.9/5
(75)

The critical path of this network is: The critical path of this network is:

(Multiple Choice)
4.8/5
(88)

   -Use the Gantt chart and activity list to determine which resource has the greatest continual use.  \begin{array} { | l | l | l | l | }  \hline \text { Activity } & \text { Resources } & \text { Activity } & \text { Resources } \\ \hline \mathbb { R } & 5 & \mathrm { M } & 1 \\ \hline \mathrm { H } & 1 & \mathrm {~K} & 5 \\ \hline \mathrm { G } & 5 & \mathrm {~J} & 3 \\ \hline \mathbb { F } & 2 & \mathrm { P } & 1 \\ \hline \mathrm { B } & 2 & \mathrm {~S} & 2 \\ \hline \mathrm { T } & 4 & \mathrm {~W} & 3 \\ \hline \end{array} -Use the Gantt chart and activity list to determine which resource has the greatest continual use. Activity Resources Activity Resources 5 1 1 5 5 3 2 1 2 2 4 3

(Multiple Choice)
4.8/5
(85)

Networks would NOT be well suited for:

(Multiple Choice)
4.7/5
(81)

Determine early start and early finish times for all activities in this network.Activity duration in days appears under each arrow. Determine early start and early finish times for all activities in this network.Activity duration in days appears under each arrow.

(Essay)
4.8/5
(79)

Gantt charts can display early start or late start logic.

(True/False)
4.9/5
(88)