Exam 6: Project Time Management
Exam 1: Introduction to Project Management100 Questions
Exam 2: The Project Management and Information Technology Context80 Questions
Exam 3: The Project Management Process Groups: A Case Study82 Questions
Exam 4: Project Integration Management100 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management100 Questions
Exam 9: Project Human Resource Management100 Questions
Exam 10: Project Communications Management99 Questions
Exam 11: Project Risk Management99 Questions
Exam 12: Project Procurement Management75 Questions
Select questions type
Activity information is not a required input to the other time management processes.
(True/False)
4.8/5
(85)
On a network diagram,all arrowheads should face toward the ____.
(Multiple Choice)
4.9/5
(84)
______________________________ involves estimating how many people,equipment,and materials a project team should use to perform project activities.
(Short Answer)
4.9/5
(83)
There are ____ main processes involved in project time management.
(Multiple Choice)
4.9/5
(87)
In the activity definition process,the project team should review the ____________________ and activity attributes with project stakeholders before moving on to the next step in project time management.
(Short Answer)
4.9/5
(79)
The ____ provide(s)schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.
(Multiple Choice)
4.7/5
(107)
Many projects,especially in information technology,have very unrealistic schedule expectations.
(True/False)
4.8/5
(77)
____ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.
(Multiple Choice)
4.8/5
(84)
The activity list,activity attributes,activity resource requirements,resource calendars,project scope statement,enterprise environmental factors,and organizational process assets all include information that affect ____.
(Multiple Choice)
4.8/5
(73)
What is a network diagram? What formats exist for creating network diagrams?
(Essay)
4.9/5
(76)
____________________ have no duration and no resources but are occasionally needed on AOA network diagrams to show logical relationships between activities.
(Short Answer)
5.0/5
(74)
Start-to-finish relationships are the most common type of relationships.
(True/False)
4.8/5
(81)
Outputs of ______________________________ include activity duration estimates and project document updates.
(Short Answer)
4.8/5
(83)
The outputs to schedule development include activity duration estimates and project document updates.
(True/False)
4.7/5
(69)
____________________ states that if something can go wrong,it will.
(Short Answer)
4.8/5
(80)
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
(Multiple Choice)
4.9/5
(80)
____________________ is the number of workdays or work hours required to complete a task.
(Short Answer)
4.9/5
(77)
Managers often cite cost issues during the end phase of a project as one of their biggest challenges and the main cause of conflict.
(True/False)
4.9/5
(78)
____ involves doing activities in parallel that you would normally do in sequence.
(Multiple Choice)
5.0/5
(73)
Critical chain scheduling protects tasks on the critical chain from being delayed by using ____,which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
(Multiple Choice)
4.8/5
(82)
Showing 81 - 100 of 100