Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Whether it is the Boeing V-22 Osprey or a simple storm door installation for a do-it-yourselfer,nothing is ever completed as quickly or as cheaply as initial estimates due to:
(Multiple Choice)
4.7/5
(94)
You are probably looking at a bill for a variable cost when you are paying for:
(Multiple Choice)
4.9/5
(83)
Define learning curve theory and describe how learning curves are used in project management.
(Essay)
4.9/5
(91)
What is the total project budget in this time-phased budget? Activity Jaruary February March April Survey 8,000 Design 5,250 4,500 Pirt 6,700 Foundation 12,550 Frarning 37,250 Plurnb 7,800 Wire 5,500
(Multiple Choice)
4.8/5
(85)
Big Mike has to prepare a bid for the swimming pools to be placed in every backyard in a new housing addition.Each swimming pool represents only a slight variation on the other,so there is a good opportunity to leverage learning effects in the bid process.A swimming pool installation can be broken down into four major steps: excavation,concrete,plumbing,and finish work.Mike has found the best contractors and asks each of them how long it will take to complete work on the first pool and what their learning rates are.Amazingly,each contractor is intimately familiar with learning curve theory and knows what his learning rate is for this type of work.This information is summarized in the table.
Furnction First Pool Learning Rate Excavation 22 hours .95 Concrete 32 hours .90 Plumbing 10 hours .85 Finishirg 30 hours .85 How long will it take to complete the 25th pool for the subdivision?
How long will it take to complete all 25 pools for the subdivision?
(Essay)
5.0/5
(65)
What is the total project budget in this time-phased budget? Activity July August Septernber October Novernber RFP 34,721 Aralysis 11,049 33,655 34,388 Pesiggn 33,718 34,474 26,759 36,328 Codirg 7,713 34,905 40,244 Testing 40,916 896 Trairing 20,958 9,327 Roll-Out 8,186
(Multiple Choice)
4.9/5
(75)
What is the total amount budgeted for design costs in this time-phased budget? Activity Jaruary February March April Survey 8,000 Design 5,250 4,500 Pirt 6,700 Foundation 12,550 Frarning 37,250 Plurnb 7,800 Wire 5,500
(Multiple Choice)
4.9/5
(76)
Activity-based costing and bottom-up budgeting share the step of:
(Multiple Choice)
4.7/5
(66)
Unplanned costs incurred when steps are taken to speed up a project's completion are called:
(Multiple Choice)
4.8/5
(86)
What is the cumulative cost in February in this time-phased budget? Activity Jaruary February March April Survey 8,000 Design 5,250 4,500 Pirt 6,700 Foundation 12,550 Frarning 37,250 Plurnb 7,800 Wire 5,500
(Multiple Choice)
4.9/5
(86)
Material is an example of a cost that is recurring,variable and direct.
(True/False)
4.7/5
(70)
What are four major categories of costs? Provide descriptions for each category.
(Essay)
4.7/5
(75)
A budget containing disaggregated figures across the schedule when work is planned is a:
(Multiple Choice)
4.9/5
(82)
Analogous estimation is a type of ________ estimating method.
(Multiple Choice)
4.9/5
(72)