Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
An activity with a learning rate of 0.8 takes 30 hours for the first six units.How long will it take to complete this task for the 12th time?
(Multiple Choice)
4.7/5
(71)
The project management research in brief titled "Delusion and Deception Taking Place in Large Infrastructure Projects," describes three reasons that cost overruns occur in large infrastructure project work.Briefly describe these three reasons
(Essay)
4.7/5
(74)
Explain the difference between normal and expedited costs,fixed and variable costs,and recurring or nonrecurring costs.Create a 2 × 2 × 2 matrix and provide one example each (8 total examples)of each combination of these costs.
(Essay)
4.8/5
(82)
It began as a simple macro that would extract grades and post them on a web site,but once the web programmer began the work,he became obsessed with various charting features,grade summaries,and reports that could be added to make this the grandest web site in the tri-county area.As 2 hours of programming work grew to 20 and then 80,he knew that the client wouldn't be happy with the cost overrun.The only comment he mumbled as he finished his work was:
(Multiple Choice)
5.0/5
(78)
Once most of the design work is complete,at a point when the scope and capabilities of the project are quite well understood,a ________ may be developed.
(Multiple Choice)
4.7/5
(91)
If it takes 40 hours to complete the first unit and the company knows from experience that the learning rate should be 0.75,how fast can they be expected to finish all ten units?
(Multiple Choice)
4.8/5
(66)
A budget contingency of $1 million on a $10 million project means that the project will be planned for a cost of $10 million,but the project organization receives an extra $1 million to guard against unforeseen cost overruns.
(True/False)
4.8/5
(89)
It took 44 hours of analysis to complete the first phase,but the second phase was done in 42 hours.If this learning rate continues,then the 8th analysis should take a mere:
(Multiple Choice)
4.8/5
(79)
What is a budget contingency and what are three reasons it might be useful?
(Essay)
4.7/5
(79)
What is the total amount budgeted for March in this time-phased budget? Activity Jaruary February March April Survey 8,000 Design 5,250 4,500 Pirt 6,700 Foundation 12,550 Frarning 37,250 Plurnb 7,800 Wire 5,500
(Multiple Choice)
4.8/5
(77)
Normal conditions,by definition,occur the vast majority of the time in project management.
(True/False)
4.8/5
(69)
Which of the following is NOT contained in a typical time-phased budget?
(Multiple Choice)
5.0/5
(66)
A plan that identifies the allocated resources,the project's goals,and the schedule that allows an organization to achieve those goals is:
(Multiple Choice)
4.8/5
(73)
If a project manager is using a similar,past project as a basis to estimate costs for a new project,he or she is utilizing analogous estimating.
(True/False)
4.7/5
(75)
A learning rate of 90% means that for every doubling of output,the time required by the activity falls by 10%.
(True/False)
4.9/5
(80)
Showing 21 - 40 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)