Exam 7: Monitoring and Controlling Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Provide a definition for a control chart and describe how control charts are used.

(Essay)
4.9/5
(74)

Projects should have a change-control system that defines procedures for changing the cost baseline.

(True/False)
4.8/5
(70)

Cause-and-effect diagrams help you find the ____________________ cause of quality problems.

(Short Answer)
4.9/5
(80)

You cannot control the scope of a project unless you have first clearly defined the scope and set a scope verification process in place.

(True/False)
4.8/5
(86)

Which of the following actions will most likely improve team productivity?

(Multiple Choice)
4.7/5
(66)

By adding all of the ____ for all project activities,you can determine how the project as a whole is performing and forecast both when it will be completed and how much it will cost at completion.

(Multiple Choice)
4.8/5
(73)

Project management software offers color ____________________ as well as numerous reports to show schedule performance information.

(Short Answer)
4.7/5
(80)

Project teams sometimes use ____-unplanned responses to risk events-when they do not have contingency plans in place.

(Multiple Choice)
4.8/5
(76)

Project risk management stops with the initial risk analysis.

(True/False)
4.8/5
(78)

You may only use earned value management at a summary level.

(True/False)
4.8/5
(82)

Earned value (EV)is an estimate of the value of physical work that is yet to be completed.

(True/False)
4.8/5
(80)

In the context of earned value management,the ____________________ is the percentage of actual work completed divided by the percentage of work planned to have been completed at any given time.

(Short Answer)
4.9/5
(81)

Describe the process of monitoring and controlling project work.

(Essay)
4.9/5
(83)

The main procurement management task performed to monitor and control projects is administering the ____.

(Multiple Choice)
4.9/5
(97)

Evaluation of any change to a project should include an impact analysis.

(True/False)
4.8/5
(88)

The cost ____________________,performance reports,change requests,and project funding requirements are inputs to the cost-control process.

(Short Answer)
4.8/5
(82)

Contract ____ includes the contract itself along with requested unapproved contract changes and approved change requests.

(Multiple Choice)
4.9/5
(86)

A red diamond on the tracking Gantt chart represents a slipped milestone.

(True/False)
4.9/5
(75)

The main monitoring and controlling task performed as part of project cost management is ____ control.

(Multiple Choice)
4.7/5
(89)

____ change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.

(Multiple Choice)
4.8/5
(75)
Showing 61 - 80 of 90
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)