Exam 5: Planning Projects, part 2 Project Quality, human Resource, communications, risk, and Procurement Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

One side (axis)of a(n)____________________/impact matrix or chart lists the relative probability of a risk event occurring,and the other side (axis)of the chart shows the relative impact of the risk event occurring.

Free
(Short Answer)
4.8/5
(73)
Correct Answer:
Verified

probability

There are ____ important dimensions of risk events.

Free
(Multiple Choice)
4.8/5
(81)
Correct Answer:
Verified

A

Two important metrics related to the Just-In-Time Training project include the ____ and course evaluation ratings.

Free
(Multiple Choice)
4.8/5
(79)
Correct Answer:
Verified

B

____ pricing can be used in various types of contracts to require the buyer to pay the supplier a predetermined amount per unit of service.

(Multiple Choice)
4.8/5
(81)

The salaries for people working directly on a project and materials purchased for a specific project are indirect costs.

(True/False)
4.8/5
(66)

Identify eight items that should be addressed by a communications management plan.

(Essay)
4.8/5
(79)

People determine the success and failure of organizations and projects.

(True/False)
4.9/5
(71)

Quality,human resource,communications,risk,and procurement management are incidental to project success.

(True/False)
4.9/5
(68)

Risk management planning addresses procurement-related topics,such as preparing risk-related ____________________ agreements.

(Short Answer)
4.9/5
(65)

Describe several functions that may be performed using a RAM (responsibility assignment matrix).

(Essay)
4.8/5
(74)

Unlike other project plans,the contents of the procurement management plan do not vary with project needs.

(True/False)
4.7/5
(87)

Three broad categories of contracts are fixed price,or lump sum; ____; and time and material.

(Multiple Choice)
4.9/5
(85)

A(n)____________________ is a list of items to be noted or consulted.

(Short Answer)
5.0/5
(66)

Contingency reserves or contingency ____________________ are funds held by the project sponsor that can be used to mitigate cost or schedule overruns if unknown risks occur.

(Short Answer)
4.7/5
(68)

You can help identify the root cause of problems by creating a cause-and-effect or ____ diagram.

(Multiple Choice)
4.8/5
(91)

Some organizations,including Global Construction,use RACI charts-a type of responsibility assignment matrix that shows Responsibility,____,Consultation,and Informed roles for project stakeholders.

(Multiple Choice)
4.7/5
(80)

Suppose that the purchase price for a piece of equipment is $12,000,with operational costs of $400 per day.If the same equipment can be leased for $800 per day (inclusive of operational costs),after how many days will the lease cost equal the purchase cost?

(Multiple Choice)
4.7/5
(75)

Project managers should include clauses in contracts to help manage project risks.

(True/False)
4.7/5
(69)

Project human ____________________ management is concerned with making effective use of the people involved with a project.

(Short Answer)
4.9/5
(76)

A(n)____________________ is a standard of measurement.

(Short Answer)
4.9/5
(75)