Exam 5: Planning Projects, part 2 Project Quality, human Resource, communications, risk, and Procurement Management
Exam 1: An Introduction to Project, program, and Portfolio Management75 Questions
Exam 2: Project, program, and Portfolio Selection75 Questions
Exam 3: Initiating Projects75 Questions
Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management100 Questions
Exam 5: Planning Projects, part 2 Project Quality, human Resource, communications, risk, and Procurement Management92 Questions
Exam 6: Executing Projects96 Questions
Exam 7: Monitoring and Controlling Projects90 Questions
Exam 8: Closing Projects and Best Practices50 Questions
Select questions type
Good procurement management typically involves buyers and sellers in a zero-sum game.
(True/False)
4.8/5
(85)
As the business world continues to become more competitive and ____,more and more projects include procurement.
(Multiple Choice)
4.8/5
(80)
A Request for ____ is a document used to solicit quotes or bids from prospective suppliers.
(Multiple Choice)
4.7/5
(63)
Work done by outside suppliers or sellers should be well documented in ____________________,which are mutually binding agreements that obligate the seller to provide the specified products or services,and obligate the buyer to pay for them.
(Short Answer)
4.8/5
(71)
A risk ____________________ is a document that contains results of various risk management processes,often displayed in a table or spreadsheet format.
(Short Answer)
4.8/5
(63)
The project manager ultimately decides what level of quality is acceptable.
(True/False)
4.8/5
(81)
A weighted scoring model provides a systematic process for selection based on numerous criteria.
(True/False)
5.0/5
(72)
The International Organization for Standardization (ISO)defines ____________________ as "the degree to which a set of inherent characteristics fulfill requirements" (ISO9000:2000).
(Short Answer)
4.7/5
(79)
____________________ plans are predefined actions that the project team will take if an identified risk event occurs.
(Short Answer)
4.9/5
(87)
A(n)____ is a document in which sellers describe what they will do to meet the requirements of a buyer.
(Multiple Choice)
4.9/5
(65)
The communications management plan for any project should always be expressed in written form.
(True/False)
4.7/5
(92)
There can be one or more potential responses to each risk event.
(True/False)
4.9/5
(80)
Project teams can develop project Web sites using Web-____ tools,such as Microsoft FrontPage or SharePoint Designer 2007 or Macromedia Dreamweaver; enterprise project management software,if available; or a combination of the two approaches.
(Multiple Choice)
4.8/5
(79)
The ____________________ cause of a problem is the real or underlying reason a problem occurs.
(Short Answer)
4.7/5
(68)
A(n)____ histogram is a column chart that shows the number of resources required for or assigned to a project over time.
(Multiple Choice)
5.0/5
(89)
A bid is a document prepared by buyers providing pricing for standard items that have been clearly defined by the seller.
(True/False)
4.9/5
(81)
____ risk events include completing work sooner than planned or at an unexpectedly reduced cost,collaborating with suppliers to produce better products,and obtaining good publicity from the project.
(Multiple Choice)
4.9/5
(79)
Risk management contributes very little to the chance of a project succeeding.
(True/False)
4.7/5
(78)
____________________ for use means that a product can be used as it was intended.
(Short Answer)
4.7/5
(81)
Time-and-____ contracts are a hybrid of both fixed-price and cost reimbursable contracts.
(Multiple Choice)
4.8/5
(74)
Showing 61 - 80 of 92
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)