Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A large percentage of total project costs are often labor costs.

(True/False)
4.8/5
(94)

A(n)____________________ diagram is a schematic display of the logical relationships among,or sequencing of,project activities.

(Short Answer)
4.8/5
(71)

The critical path is the shortest path through the network diagram.

(True/False)
4.9/5
(75)

Performance in meeting project scope goals is based on the scope ____.

(Multiple Choice)
5.0/5
(77)

There are ____ basic reasons for creating dependencies among project activities.

(Multiple Choice)
4.8/5
(92)

Project management software uses the ____ format to represent the WBS.

(Multiple Choice)
4.9/5
(83)

After you determine the reason for a dependency between activities,you must determine the type of dependency.

(True/False)
4.7/5
(67)

____ estimates,also called top-down estimates,use the actual cost of a previous,similar project as the basis for estimating the cost of the current project.

(Multiple Choice)
4.9/5
(77)

Project teams rarely estimate completion dates for milestones early in the scheduling process.

(True/False)
4.8/5
(96)

The main planning tasks performed as part of project scope management include scope planning,scope definition,and ____.

(Multiple Choice)
4.9/5
(85)

To create a good WBS,you must understand both the project and its scope,and incorporate the needs and knowledge of the ____________________.

(Short Answer)
4.8/5
(88)

____________________-also called critical path analysis-is a network diagramming technique used to predict total project duration.

(Short Answer)
4.8/5
(83)

What are some important questions to answer in activity resource estimating?

(Essay)
4.9/5
(94)

In an AOA network diagram,____ occur when two or more activities follow a single node.

(Multiple Choice)
5.0/5
(78)

To define the ____ of the project accurately,it is very important to ensure consistency between the project charter,scope statement,WBS,Gantt chart,and related documents.

(Multiple Choice)
4.9/5
(72)

A dependency or ____________________ relates to the sequencing of project activities or tasks.

(Short Answer)
4.8/5
(75)

You need to plan the project ____________________ and determine what activities need to be done before you can develop a detailed project schedule.

(Short Answer)
4.8/5
(93)

Slack or ____ is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date.

(Multiple Choice)
4.8/5
(84)

Tasks in a WBS that are decomposed into smaller tasks are called ____ tasks.

(Multiple Choice)
5.0/5
(70)

A three-point estimate is an estimate that includes a(n)____,most likely,and pessimistic estimate,such as three weeks,four weeks,and five weeks,respectively.

(Multiple Choice)
4.8/5
(63)