Exam 1: The World of Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When using the weighted scoring model, the categories for each scale must be in equal intervals.

(True/False)
4.8/5
(80)

As a rule of thumb, the number of factors included in a scoring model should be at least 10.

(True/False)
4.7/5
(88)

A disadvantage of using the payback period method for selecting projects is that it cannot reflect the time-value of money.

(True/False)
4.8/5
(91)

Projects with deliverables that are incrementally different from existing offerings are classified as platform projects.

(True/False)
4.9/5
(89)

Projects in which team members may never physically meet before the team is disbanded and another team reconstituted is called a virtual team

(True/False)
4.8/5
(89)

If a PM manages her project well enough she can eliminate uncertainty.

(True/False)
4.9/5
(73)

One of the few similarities between project management and general management is that both exist in the well-defined organizational structure of superior/subordinates in the overall organization.

(True/False)
4.9/5
(82)

Projects success is not determined by the portfolio of projects in an organization..

(True/False)
4.8/5
(84)

The aggregate project plan can be used for the following except:

(Multiple Choice)
4.8/5
(74)

Which of the following is not a characteristic of a project?

(Multiple Choice)
4.8/5
(76)

Which of the following is a nonnumeric project selection method?

(Multiple Choice)
4.8/5
(76)

Which of the following is not related to the three goals of a project?

(Multiple Choice)
4.9/5
(77)

As the present value of future returns decreases with rising discount rates, firms with high hurdle rates favor short-run projects.

(True/False)
4.8/5
(72)

In the early years of a project when outflows usually exceed inflows, the NPV of the project for those years will be positive.

(True/False)
4.7/5
(86)

Briefly differentiate between derivative and breakthrough projects as defined by Wheelwright and Clark.

(Essay)
4.8/5
(70)

Why is having a negotiation skill in win-win negotiation necessary for the project manager?

(Essay)
4.8/5
(87)

Nonnumeric project selection methods are only suitable if numeric methods are not available.

(True/False)
5.0/5
(84)

Many recent developments in project management are being driven by changes in the nature of the American workforce.

(True/False)
4.9/5
(76)

The ________________________ attempts to link the organization's projects directly to the goals and strategy of the organization.

(Multiple Choice)
4.9/5
(77)

Briefly describe the two different life cycles of projects.

(Not Answered)
This question doesn't have any answer yet
Ask our community
Showing 41 - 60 of 70
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)