An identifiable state resulting from the completion of one or more activities is called?

Free
(Multiple Choice)
4.8/5
(86)
Correct Answer:
Verified

A

What is it a milestone?

Free
(Multiple Choice)
4.9/5
(73)
Correct Answer:
Verified

A

A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.

Free
(True/False)
4.8/5
(80)
Correct Answer:
Verified

False

Define the term Critical Path.

(Short Answer)
4.8/5
(78)

An event is a series of connected activities.

(True/False)
5.0/5
(89)

Standard Pert/CPM networks can be use to resolve probabilistic concerns.

(True/False)
4.9/5
(88)

What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?

(Multiple Choice)
4.8/5
(83)

The difference between the LST and EST is called slack.

(True/False)
4.8/5
(82)

The difference between LST and LFT is called slack.

(True/False)
4.7/5
(64)

Another name for total slack is free slack.

(True/False)
4.9/5
(85)

Events in a project consume no resources or time.

(True/False)
4.9/5
(60)

Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.

(True/False)
4.8/5
(73)

The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a Beta distribution.

(True/False)
4.8/5
(70)

Slack is calculated as?

(Multiple Choice)
4.7/5
(81)

Which of the following is typically used as the best estimate of task duration?

(Multiple Choice)
5.0/5
(90)

What are the four methods of linking steps in a project using precedence diagramming?

(Not Answered)
This question doesn't have any answer yet
Ask our community

A start-to-finish linkage is the most common way of linking to successive task.

(True/False)
4.8/5
(65)

Which of the following terms is most closely associated with a task required by the project?

(Multiple Choice)
4.9/5
(74)

The simulation approach is generally preferred over the statistical method.

(True/False)
4.8/5
(88)

Milestones cannot be identified on a Gantt Chart.

(True/False)
4.8/5