Exam 17: MRP and ERP

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The MRP input listing the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product is the:

(Multiple Choice)
4.9/5
(70)

The MRP input stating which end items are to be produced, when they are needed, and what quantities are needed, is the:

(Multiple Choice)
4.8/5
(69)

In MRP, the gross requirements of a given component part are calculated directly from:

(Multiple Choice)
4.9/5
(67)

A visual depiction of the subassemblies and components that are needed to produce and/or assemble a product is called a(n):

(Multiple Choice)
5.0/5
(67)

The master schedule needs to be for a period long enough to cover the stacked or cumulative lead time necessary to produce the end items.

(True/False)
4.9/5
(66)

The output of MRP is:

(Multiple Choice)
4.8/5
(89)

Safety time is sometimes used in MRP rather than safety stock quantities.

(True/False)
4.9/5
(63)

An assembly-time chart indicates gross and net requirements taking into account the current available inventory.

(True/False)
4.9/5
(77)

Refer to this product tree: Refer to this product tree:   If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed? If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed?

(Multiple Choice)
4.8/5
(64)

The _________ of ERP makes it valuable as a strategic planning tool.

(Multiple Choice)
4.8/5
(85)

Lot-for-lot ordering in MRP provides coverage for some predetermined number of periods (such as two or three) that extend beyond the orders already received for those periods.

(True/False)
4.7/5
(80)

Net requirements for component J are as follows: 60 units in week 2, 40 units in week 3, and 60 units in week 5. If a fixed-period, two-period lot-sizing method is used, what will be the quantity of the first planned receipt?

(Multiple Choice)
4.9/5
(71)

Refer to this product tree: Refer to this product tree:   If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed? If 17 Ps are needed, and on-hand inventory consists of 10 As, 15 Bs, 20 Cs, 12 Ms, and 5 Ns, how many Cs are needed?

(Multiple Choice)
4.9/5
(74)

In a master schedule, the planning horizon is often separated into a series of time periods called:

(Multiple Choice)
4.7/5
(72)

MRP works best if the inventory items have dependent demand.

(True/False)
4.8/5
(76)

Which of these items would be most likely to have dependent demand?

(Multiple Choice)
4.9/5
(73)

Which one of the following most closely describes the MRP approach that is used for components or subassemblies to compensate for variations in lead time?

(Multiple Choice)
4.9/5
(79)

Capacity requirements planning helps managers reconcile __________ with __________.

(Multiple Choice)
4.8/5
(73)

MRP output reports are divided into two main groups, daily and weekly.

(True/False)
4.8/5
(78)

Which of the following represents an attempt to balance the benefits of stability in the production plan against the benefits of responding quickly to new orders?

(Multiple Choice)
4.9/5
(93)
Showing 61 - 80 of 81
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)