Exam 1: Certified Authorization Professional
Exam 1: Certified Authorization Professional313 Questions
Exam 2: Certified Cloud Security Professional (CCSP)501 Questions
Exam 3: Certified Information Systems Security Professional336 Questions
Select questions type
The National Information Assurance Certification and Accreditation Process (NIACAP) is the minimum standard process for the certification and accreditation of computer and telecommunications systems that handle U.S. national security information. What are the different types of NIACAP accreditation? Each correct answer represents a complete solution. Choose all that apply.
(Multiple Choice)
4.8/5
(72)
Which of the following assessment methodologies defines a six-step technical security evaluation?
(Multiple Choice)
4.8/5
(79)
Which of the following individuals is responsible for the final accreditation decision?
(Multiple Choice)
4.9/5
(65)
Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?
(Multiple Choice)
4.8/5
(87)
Which of the following roles is responsible for review and risk analysis of all contracts on a regular basis?
(Multiple Choice)
4.9/5
(69)
The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully integrated system for certification testing and accreditation. What are the process activities of this phase? Each correct answer represents a complete solution. Choose all that apply.
(Multiple Choice)
4.7/5
(93)
Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?
(Multiple Choice)
4.9/5
(79)
FITSAF stands for Federal Information Technology Security Assessment Framework. It is a methodology for assessing the security of information systems. Which of the following FITSAF levels shows that the procedures and controls have been implemented?
(Multiple Choice)
4.9/5
(68)
ISO 17799 has two parts. The first part is an implementation guide with guidelines on how to build a comprehensive information security infrastructure and the second part is an auditing guide based on requirements that must be met for an organization to be deemed compliant with ISO 17799. What are the ISO 17799 domains? Each correct answer represents a complete solution. Choose all that apply.
(Multiple Choice)
4.9/5
(83)
John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?
(Multiple Choice)
4.8/5
(79)
Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?
(Multiple Choice)
4.8/5
(73)
The Phase 3 of DITSCAP C&A is known as Validation. The goal of Phase 3 is to validate that the preceding work has produced an IS that operates in a specified computing environment. What are the process activities of this phase? Each correct answer represents a complete solution. Choose all that apply.
(Multiple Choice)
4.8/5
(82)
Sam is the project manager of a construction project in south Florida. This area of the United States is prone to hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge the possibility of hurricanes and the damage the hurricane could have on the project's deliverables, the schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen. What type of risk response is Sam using?
(Multiple Choice)
4.9/5
(76)
James work as an IT systems personnel in SoftTech Inc. He performs the following tasks: Runs regular backups and routine tests of the validity of the backup data. Performs data restoration from the backups whenever required. Maintains the retained records in accordance with the established information classification policy. What is the role played by James in the organization?
(Multiple Choice)
4.7/5
(80)
Which of the following administrative policy controls requires individuals or organizations to be engaged in good business practices relative to the organization's industry?
(Multiple Choice)
4.8/5
(79)
Which of the following documents is used to provide a standard approach to the assessment of NIST SP 800-53 security controls?
(Multiple Choice)
4.9/5
(90)
Jeff, a key stakeholder in your project, wants to know how the risk exposure for the risk events is calculated during quantitative risk analysis. He is worried about the risk exposure which is too low for the events surrounding his project requirements. How is the risk exposure calculated?
(Multiple Choice)
4.9/5
(90)
What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?
(Multiple Choice)
5.0/5
(82)
You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?
(Multiple Choice)
5.0/5
(86)