You Are the Project Manager for Your Organization

Question 160

Multiple Choice

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?


A) Secondary risk
B) Transference
C) Internal
D) Pure risk

Correct Answer: