Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on the project. Bill discusses the risk event with Virginia, the primary project customer, and she decides that the requirements surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high risk exposure. What risk response has been enacted in this project?
A) Acceptance
B) Mitigation
C) Avoidance
D) Transference
Correct Answer:

Verified
Correct Answer:
Verified
Q156: Which of the following administrative policy controls
Q157: Which of the following documents is used
Q158: Jeff, a key stakeholder in your project,
Q159: What project management plan is most likely
Q160: You are the project manager for your
Q162: Which of the following acts promote a
Q163: Which of the following assessment methodologies defines
Q164: Which of the following acts is used
Q165: Which of the following NIST documents defines
Q166: Which of the following NIST C&A documents