Exam 6: Process Selection and Facility Layout
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
Which of the following is not true about process layouts when they are compared to product layouts?
(Multiple Choice)
4.9/5
(87)
A company needs to locate three departments (X, Y, and Z)in the three areas (I, II, and III)of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $0.50 per load per meter moved. An analyst has prepared the following distances and flow matrices:
What is the total flow (loads per week)between department Y and department Z?
(Multiple Choice)
4.7/5
(84)
"Balance delay" is another name for the percentage of idle time in a product layout.
(True/False)
4.7/5
(89)
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product:
For output to equal projected demand, what should be the actual cycle time for this assembly line?
(Multiple Choice)
4.9/5
(65)
In the use of closeness ratings for process layouts, the code U means the closeness between two departments is
(Multiple Choice)
4.8/5
(92)
Although they do not guarantee optimal solutions, _____ are useful in finding reasonable solutions when the number of possible options is overwhelming.
(Multiple Choice)
4.8/5
(81)
The type of layout in which workers, materials, and equipment are moved to the product as needed is
(Multiple Choice)
4.8/5
(67)
Product profiling links key product or service requirements to
(Multiple Choice)
4.9/5
(71)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line 8 hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a case of Mint Chocolate Chip Cookies.
For output to equal projected demand, what will be the first task performed at the third workstation of the production line which uses the minimum number of stations?
(Multiple Choice)
4.9/5
(73)
Which of the following does not reflect lean process design general principles?
(Multiple Choice)
4.8/5
(70)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line 8 hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a case of Mint Chocolate Chip Cookies.
For output to equal projected demand, what should be the actual cycle time for this production line?
(Multiple Choice)
4.8/5
(78)
A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
Without regard to demand, what is the minimum possible cycle time (in seconds)for this situation?
(Multiple Choice)
4.9/5
(77)
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product:
For output to equal projected demand, what will be the idle time at the second workstation of the assembly line that uses the minimum number of workstations?
(Multiple Choice)
4.8/5
(79)
Which of the following is not an approach that companies use to achieve a smooth flow of production?
(Multiple Choice)
4.8/5
(70)
What is it about repetitive processes that make them appropriate for products in the maturity phase of their life cycle?
(Multiple Choice)
4.8/5
(79)
Mismatches between operational capabilities and market demand can have a negative impact on an organization.
(True/False)
4.9/5
(69)
The minimum possible cycle time in a typical product layout with no parallel activities is determined by the
(Multiple Choice)
4.8/5
(66)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line 8 hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a case of Mint Chocolate Chip Cookies.
For output to equal projected demand, what will be the efficiency of the production line that uses the theoretical minimum number of workstations?
(Multiple Choice)