Exam 24: Supplement G Acceptance Sampling Plans
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
A double-sampling plan has n₁ = 50, n₂ = 100, c₁ = 2, and c₂ = 4. Suppose on the first sample, five defectives were discovered. How many total items will be inspected before a decision is reached?
(Multiple Choice)
4.8/5
(63)
A small ________ can be disregarded in AOQ calculations involving an extremely large lot size.
(Short Answer)
4.8/5
(80)
What is the basic idea of incoming inspection? Why does a producer perform it?
(Essay)
4.9/5
(97)
In general, a sequential sampling strategy will require a lower number of items be inspected if the actual percentage of defectives in the lot is ________.
(Short Answer)
4.9/5
(90)
A double-sampling plan requires two sample sizes and two acceptance numbers.
(True/False)
4.8/5
(81)
A single-sampling plan by attributes is needed for a purchased component. Given the following information, what is the consumer's risk? Table G.1 is appended to this exam. Sample size = 75
Acceptance number (c) = 3
Acceptance quality level (AQL) = 0.01
Lot tolerance proportion defective (LTPD) = 0.05
(Multiple Choice)
4.8/5
(69)
The distance between 1.0 and where the AQL intersects the OC curve is the value β (Beta).
(True/False)
4.8/5
(79)
If you were interested in minimizing the average number of items inspected, which type of sampling plan would you choose? Why?
(Essay)
4.9/5
(74)
An operating characteristic curve is a plot of the probability of accepting the lot against the proportion defectives.
(True/False)
4.8/5
(89)
A single-sampling plan by attributes is needed for a purchased component. Given the following information, what is the consumer's risk? Table G.1 is appended to this exam. Sample size = 75
Acceptance number (c) = 2
Acceptance quality level (AQL) = 0.01
Lot tolerance proportion defective (LTPD) = 0.05
(Multiple Choice)
4.7/5
(92)
If the sample size is increased and the acceptance level is unchanged, the OC curve will have a slope that is more negative.
(True/False)
4.9/5
(68)
A single-sampling plan has the following performance:
What is the average outgoing quality limit if the sample size is 200 and the lot size is 6,000?
(Multiple Choice)
4.8/5
(78)
A single-sampling plan by attributes is needed for a purchased component. Given the following information, what is the consumer's risk? Table G.1 is appended to this exam. Sample size = 50
Acceptance number (c) = 3
Acceptance quality level (AQL) = 0.01
Lot tolerance proportion defective (LTPD) = 0.04
(Multiple Choice)
4.9/5
(74)
A lot of 1,000 items is on the loading dock. A single-sampling plan calls for a sample size of 10. The following table gives the probability of acceptance for the plan over a range of possible quality levels.
What is the average outgoing quality limit for this plan?
(Multiple Choice)
4.8/5
(79)
________ is the risk that the sampling plan will fail to verify an acceptable lot's quality and thus reject it-a type I error.
(Short Answer)
4.8/5
(80)