Exam 9: Variance Analysis: Revenue and Cost
Exam 1: The Role of Accounting Information in Management Decision Making92 Questions
Exam 2: Cost Concepts, Behaviour and Estimation128 Questions
Exam 3: A Costing Framework and Cost Allocation91 Questions
Exam 4: Costvolumeprofit Cvp Analysis106 Questions
Exam 5: Planning Budgeting and Behaviour91 Questions
Exam 6: Operational Budgets104 Questions
Exam 7: Job and Process Costing Systems154 Questions
Exam 8: Flexible Budgets, Standard Costs and Variance Analysis76 Questions
Exam 9: Variance Analysis: Revenue and Cost157 Questions
Exam 10: Activity Analysis: Costing and Management135 Questions
Exam 11: Relevant Costs for Decision Making193 Questions
Exam 12: Strategy and Control35 Questions
Exam 13: Capital Budgeting and Strategic Investment Decisions93 Questions
Exam 14: The Strategic Management of Costs and Revenues109 Questions
Exam 15: Strategic Management Control: a Lean Perspective46 Questions
Exam 16: Responsibility Accounting, Performance Evaluation and Transfer Pricing63 Questions
Exam 17: The Balanced Scorecard and Strategy Maps83 Questions
Exam 18: Rewards, Incentives and Risk Management45 Questions
Exam 19: Sustainability Management Accounting45 Questions
Select questions type
In Command Ltd completed operations for the week and the accountant was preparing to make journal entries necessary to prepare a set of interim financial statements. Unfortunately, he discovered some of the data concerning direct materials had been lost. He was able to find the following: Efficiency variance \ 9,000 Unfavourable Stardard price \ 10 per urit Actual units purchased 18,000 Inventory decrease 1,000 units Budget variance \ 1,800 Favourable The actual direct materials price paid per unit was:
(Multiple Choice)
4.7/5
(76)
The variable overhead spending variance is the difference between actual variable overhead costs and the expected variable overhead costs for the actual use of the allocation base.
(True/False)
4.9/5
(83)
If manufacturing cost variances are considered to be material the preferred treatment is to pro rata the variance to work in process, finished goods inventory and cost of sales.
(True/False)
4.9/5
(90)
The journal entry to record the use of direct materials for Aztec Bromac is:
(Multiple Choice)
4.9/5
(79)
The market share variance provides an indication of the changes in contribution margin due to selling a different mix of products than planned.
(True/False)
4.8/5
(83)
Castinata Co. uses a standard job cost system and a denominator volume of 25,000 direct labour hours for allocating overhead. The actual output was 12,000 units, which cost $185,700 for direct labour (23,000 hours), $28,000 for variable overhead, and $150,000 for fixed overhead.
The standard variable overhead per unit is $2 (2 hours @ $1 per hour), and the standard fixed overhead per unit is $10 (2 hours @ $5 per hour).
All variances are immaterial and are closed to Cost of Sales at the end of the period.
The entry to close the variable overhead variances includes a:
(Multiple Choice)
4.9/5
(82)
The information required for the market size variance is collected by the marketing department.
(True/False)
4.8/5
(82)
Tycoon Manufacturing uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 5,000 units monthly. Overhead costs were estimated to be $250,000. The standard variable overhead rate is $5 per machine hour. During October the following results were recorded:
Units produced 4,900 Units sold 4,600 Machine hours required 20,500 Actual overhead cost \ 248,000
The fixed overhead production volume variance was:
(Multiple Choice)
4.7/5
(80)
During the period Cash Spinner produced 2,000 units of product. The flexible budget for standard costs is: Direct materials \ 43,000 Direct labor 67,000 Variable overhead 30,000 Fixed overhead 25,000 Variances for the period are: Direct materials price \ 400 Direct materials efficiency 500 Direct labor price 600 Direct labor efficiency 200 Variable overhead spending 300 Variable overhead efficiency 100 Fixed overhead spending 500 Fixed overhead production volume 1,000
The direct materials inventory increased during the period by 500 (at standard cost). The variable overhead allocated was:
(Multiple Choice)
4.7/5
(83)
In standard costing the price and efficiency variances account for the differences between actual and standard costs in the ledger accounts.
(True/False)
4.9/5
(83)
Fixed costs remain the same for both the budgeted level of volume and the static budget level of volume.
(True/False)
4.8/5
(88)
Misc Ltd entered into a new contract with one of its raw material suppliers. The new contract required the supplier to deliver raw materials with a 24-hour notice from Misc. This reduces Misc's material handling costs, but has increased the cost of the raw materials delivered. Which of the following variances is most likely to result?
(Multiple Choice)
4.9/5
(87)
The direct materials efficiency variance is favourable when direct materials used is less than expected for the actual level of output.
(True/False)
4.9/5
(84)
Aztec Bromac budgeted the following cost standards for the current year: Direct materials = 2.8 kilos per unit @ $3.00 per kilo
Direct labour = 1.5 hours per unit @ $6 per hour
Actual production and costs were as follows:
Units produced = 3,600
Direct materials used = 9,000 kg.
Direct materials purchased = 10,000 kg. @ a cost of $29,000
Direct labour incurred = 4,000 hours at a cost of $26,000
The material efficiency variance was:
(Multiple Choice)
4.9/5
(68)
Scenesay Ltd is a capital intensive firm. Indirect costs make up nearly 70% of the product costs. The company has no direct material costs because customers provide the direct materials used for each job. To plan and control such costs, the firm employs flexible budgets and standard costs. Overhead rates, based on direct labour hours, are derived from the master budget. Master Budget Actual Results Units produced 4,000 3,620 Direct Labour Hours 10,000 11,000 Fixed Overhead \ 200,000 \ 205,000 Variable Overhead \ 320,000 \ 355,000 Direct Labour \ 200,000 \ 180,000 The direct labour efficiency variance was:
(Multiple Choice)
4.9/5
(92)
The sales price variance is caused by a difference in the volume of units sold.
(True/False)
5.0/5