Exam 10: Standard Costing: a Managerial Control Tool

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Crawford Corporation has the following information: Crawford Corporation has the following information:     Crawford Corporation has the following information:

(Essay)
4.9/5
(83)

The actual quantity of input at the actual price less the actual quantity of input at the standard price is the price variance.

(True/False)
4.9/5
(83)

Figure 10-9. James Company manufactures t-shirts.During the year,it manufactured 250,000 t-shirts,using 2 hours of direct labor at a rate of $8.50 per hour.The materials and labor standards for manufacturing the t-shirts are: Figure 10-9. James Company manufactures t-shirts.During the year,it manufactured 250,000 t-shirts,using 2 hours of direct labor at a rate of $8.50 per hour.The materials and labor standards for manufacturing the t-shirts are:   It took James 1,400,000 yards at $2.50 per yard to make the 250,000 t-shirts. Refer to Figure 10-9.What is the entry to record the purchase of materials? It took James 1,400,000 yards at $2.50 per yard to make the 250,000 t-shirts. Refer to Figure 10-9.What is the entry to record the purchase of materials?

(Multiple Choice)
4.8/5
(66)

Figure 10-9. James Company manufactures t-shirts.During the year,it manufactured 250,000 t-shirts,using 2 hours of direct labor at a rate of $8.50 per hour.The materials and labor standards for manufacturing the t-shirts are: Figure 10-9. James Company manufactures t-shirts.During the year,it manufactured 250,000 t-shirts,using 2 hours of direct labor at a rate of $8.50 per hour.The materials and labor standards for manufacturing the t-shirts are:   It took James 1,400,000 yards at $2.50 per yard to make the 250,000 t-shirts. Refer to Figure 10-9.What is James' materials price variance assuming that materials purchased equals materials used? It took James 1,400,000 yards at $2.50 per yard to make the 250,000 t-shirts. Refer to Figure 10-9.What is James' materials price variance assuming that materials purchased equals materials used?

(Multiple Choice)
4.7/5
(77)

The _______________ computes the difference between what was paid to direct laborers and what should have been paid.

(Short Answer)
4.8/5
(75)

Kaizen costing involves:

(Multiple Choice)
4.8/5
(71)

Which of the following is not an advantage of standard costing over normal costing and actual costing?

(Multiple Choice)
4.9/5
(92)

The actual quantity of input at the standard price less than the standard quantity of input at the standard price equals the usage variance.

(True/False)
4.9/5
(91)

___________________ can provide an initial guideline for setting standards,but should be used with caution because they can perpetuate existing inefficiencies.

(Short Answer)
4.8/5
(92)

Figure 10-5. Figure 10-5.   Refer to Figure 10-5.What is the materials usage variance? Refer to Figure 10-5.What is the materials usage variance?

(Multiple Choice)
4.8/5
(85)

An accountant would refer to a cost sheet to perform which of the following actions?

(Multiple Choice)
4.8/5
(72)

DuRoss Company produces coats.The company uses a standard costing system and has set the following standards for materials and labor: DuRoss Company produces coats.The company uses a standard costing system and has set the following standards for materials and labor:    During the year DuRoss produced 55,000 coats.Actual fabric purchased was 460,000 yards at $5.75 per yard.There were no beginning or ending inventories of fabric.Actual direct labor was 120,000 hours at $19.25 per hour.   During the year DuRoss produced 55,000 coats.Actual fabric purchased was 460,000 yards at $5.75 per yard.There were no beginning or ending inventories of fabric.Actual direct labor was 120,000 hours at $19.25 per hour. DuRoss Company produces coats.The company uses a standard costing system and has set the following standards for materials and labor:    During the year DuRoss produced 55,000 coats.Actual fabric purchased was 460,000 yards at $5.75 per yard.There were no beginning or ending inventories of fabric.Actual direct labor was 120,000 hours at $19.25 per hour.

(Essay)
4.8/5
(84)

The standard unit cost is developed before the standard costs for direct materials,direct labor,and overhead can be set.

(True/False)
4.8/5
(87)

The materials price variance is computed using the equation

(Multiple Choice)
4.9/5
(73)

Roberts Company uses a standard costing system.The following information pertains to direct materials for the July: Roberts Company uses a standard costing system.The following information pertains to direct materials for the July:   Roberts Company reports its material price variances at the time of purchase.What is the material usage variance for Roberts Company? Roberts Company reports its material price variances at the time of purchase.What is the material usage variance for Roberts Company?

(Multiple Choice)
4.8/5
(63)

The standard cost sheet provides the input standards needed to compute the total amount of inputs allowed for the actual output,an essential component in computing efficiency variances.

(True/False)
4.8/5
(65)

Standard costs are developed for direct materials,direct labor,and variable overhead only.

(True/False)
4.9/5
(65)

Engineering studies are often too rigorous and may not be achievable by operating personnel.

(True/False)
4.8/5
(75)

Acme Brick Company uses the following rule to determine whether materials usage variances should be investigated: A materials usage variance will be investigated when the variance is greater than either $5,000 or 10 percent of the standard cost. During June,the company purchased and used 9,500 pounds of concrete for $5 per pound.It was able to make 20,000 bricks.Its standard quantity of materials allowed is 0.45 pound of concrete per brick at a standard price of $6 per pound. Acme Brick Company uses the following rule to determine whether materials usage variances should be investigated: A materials usage variance will be investigated when the variance is greater than either $5,000 or 10 percent of the standard cost. During June,the company purchased and used 9,500 pounds of concrete for $5 per pound.It was able to make 20,000 bricks.Its standard quantity of materials allowed is 0.45 pound of concrete per brick at a standard price of $6 per pound.

(Essay)
4.8/5
(89)

Figure 10-7. During April,a small roofing company purchased 700 bundles of a certain type of shingle at a price of $35 per bundle,$8 more than the standard price.Its standard quantity of this type of shingle is 725 bundles. Refer to Figure 10-7.What is the journal entry to record the purchase of materials?

(Multiple Choice)
4.9/5
(82)
Showing 101 - 120 of 163