Deck 6: The Work Breakdown Structure and Project Estimation
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/84
Play
Full screen (f)
Deck 6: The Work Breakdown Structure and Project Estimation
1
Identifying the critical path is important because any change in the duration of the activities or tasks on the critical path will affect the project's schedule.
True
2
The direct costs of using a resource is the only type of cost that should be considered when developing the project budget.
False
3
A parallel activity is a task that can be worked on at the same time as another activity.
True
4
Once the project schedule and budget are accepted by the client or sponsor, the project plan becomes the baseline plan that will be used as a benchmark to track the project's actual progress.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
5
A start-to-finish activity is the most common relationship between two activities.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
6
Project network diagrams provide valuable information about the logical sequence and dependencies among the various activities and tasks so that a completion date or deadline can be determined.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
7
The critical path has zero slack (or float)
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
8
Predecessor activities are activities that must be completed before another activity can be started.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
9
A reserve can provide a cushion when unexpected situations arise.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
10
Installing a server before loading the operating system is an example of a finish-to-start relationship.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
11
Start-to-Start and Finish-to-Finish relationships allow activities to be worked on in parallel.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
12
Sunk costs include such things as rent, utilities, insurance, and other administrative costs.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
13
The critical path is the shortest path in the project network and also is the longest time in which the project can be completed.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
14
Identifying the critical path is important because a project can only have one critical path and it never changes.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
15
Predecessor activities are activities that can be worked on at the same time as another activity.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
16
Parallel activities can shorten the project schedule, but can have an impact on project resources if a resource is assigned to two tasks at the same time.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
17
The critical path is the longest path in the project network and also is the shortest time in which the project can be completed.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
18
The project budget is determined by the project schedule, the cost of the resources assigned to each of the tasks, and by any other direct or indirect costs and reserves.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
19
An over allocated resource would arise when Mary is assigned to work on two tasks scheduled at the same time.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
20
PERT was developed in the 1950s to create a visual representation of scheduled activities, their logical sequence, and interrelationships using a statistical probability distribution.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
21
The kick-off meeting brings closure to the planning phase of the project.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
22
An activity being analyzed under PERT was judged to most likely have a duration of 40 days.When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to be able to be doable in 20 days and even under the worst case imaginable, the task would be take 50 days.The estimates PERT duration of that activity is:
A) 36.67 days
B) 38.33 days
C) 37.50 days
D) 28.33 days
E) 32.67 days
A) 36.67 days
B) 38.33 days
C) 37.50 days
D) 28.33 days
E) 32.67 days
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
23
The tool most closely associated with activity bars across a horizontal time axis is:
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
24
A kick-off meeting is often held to develop the project plan.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
25
The technique used to find the sequence of tasks with zero slack (or float) is most closely associated with:
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
26
Starting the next task before the first task is complete is _____
A) lead
B) lag
C) negative lead
D) slack
E) float
A) lead
B) lag
C) negative lead
D) slack
E) float
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
27
The Critical Path is:
A) the longest path in the project network.
B) the shortest path in the project network.
C) the longest time in which the project can be completed.
D) the interrelationships of project activities.
E) the most important identified tasks within the project.
A) the longest path in the project network.
B) the shortest path in the project network.
C) the longest time in which the project can be completed.
D) the interrelationships of project activities.
E) the most important identified tasks within the project.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
28
Adding resources to an activity to shorten the critical path is called_____
A) slacking.
B) floating.
C) diverting.
D) crashing.
E) fast tracking
A) slacking.
B) floating.
C) diverting.
D) crashing.
E) fast tracking
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
29
The amount of time an activity can be delayed before affecting the project deadline is _____
A) slack
B) crash
C) fast-track
D) diversion
E) delay in any activity will delay the project
A) slack
B) crash
C) fast-track
D) diversion
E) delay in any activity will delay the project
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
30
Under the Precedence Diagramming Method, the most common relationship between two activities which implies a logical sequence is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
31
The technique used to help manage the Polaris submarine project and which bases activity estimates on probabilistic estimates of three scenarios is most closely associated with:
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
32
Based upon the following diagram and activity durations, the Critical Path is:


A) A+B+C+F+H+J
B) A+B+D+F+H+J
C) A+B+D+G+H+J
D) A+B+D+G+I+J
E) A+B+E+G+I+J


A) A+B+C+F+H+J
B) A+B+D+F+H+J
C) A+B+D+G+H+J
D) A+B+D+G+I+J
E) A+B+E+G+I+J
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
33
Completing activities in parallel is called_____
A) slacking.
B) floating.
C) diverting.
D) crashing.
E) fast tracking
A) slacking.
B) floating.
C) diverting.
D) crashing.
E) fast tracking
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
34
_____ can be useful for tracking and monitoring project progress because because they are simple and straightforward.
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
35
_____ is well suited for developing simulations where the project manager can conduct sensitivity analysis for schedule planning and risk analysis.
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
36
Which of the following statements are true?:
A) Milestones are logical units of work.
B) Baseline plans are approved project plans.
C) All tasks are linear, i.e. have to be completed in a particular sequence.
D) The kick-off meeting typically begins the planning phase of a project.
E) MOV are readily changed through change control processes.
A) Milestones are logical units of work.
B) Baseline plans are approved project plans.
C) All tasks are linear, i.e. have to be completed in a particular sequence.
D) The kick-off meeting typically begins the planning phase of a project.
E) MOV are readily changed through change control processes.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
37
_____ can help manage the Critical Path by providing information about which activities can be delayed without affecting the deadline target date.
A) Work Breakdown Schedule
B) Gantt Charts
C) PART
D) Project Network Diagrams
E) Critical Path Analysis
A) Work Breakdown Schedule
B) Gantt Charts
C) PART
D) Project Network Diagrams
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
38
_____ is considered the most useful and widely used project management tool.
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
39
Under the Precedence Diagramming Method, the situation which occurs when a relationship between two tasks that can or must start at the same time is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
40
_____ provide valuable information about the logical sequence and dependencies among the various activities and tasks:
A) Work Breakdown Schedule
B) Gantt Charts
C) PART
D) Project Network Diagrams
E) Critical Path Analysis
A) Work Breakdown Schedule
B) Gantt Charts
C) PART
D) Project Network Diagrams
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
41
Time and effort needed to gather experience on a technology or process are _____
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
42
Waiting to leave your shift until another person shows up is an example of:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
43
Rolling wave planning is:
A) developing a large plan encompassing all project items.
B) including the highest level of detail in project plans
C) preparing a summary plan and developing incremental detailed schedules
D) all of these
E) none of these
A) developing a large plan encompassing all project items.
B) including the highest level of detail in project plans
C) preparing a summary plan and developing incremental detailed schedules
D) all of these
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
44
Under the Precedence Diagramming Method, the situation which occurs when two activities can start at different times, have different durations, but are planned to be competed at the same time is called:
A) Finish-To-Start (FS)
A) none of these
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
A) Finish-To-Start (FS)
A) none of these
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
45
Costs incurred prior to the current project are _____
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
46
Once the project schedule and project budget are approved they become the _____
A) derivative plan
B) actual plan
C) baseline plan
D) project plan
E) schedule plan
A) derivative plan
B) actual plan
C) baseline plan
D) project plan
E) schedule plan
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
47
Critical Chain Project Management (CCPM) is based on the idea that
A) people often inflate or add cushioning to their time estimates
B) PERT/CPM was developed in the 1950s so it is too old to be of any use
C) Precedence Diagramming only considers the critical path of a project
D) all of these
E) none of these
A) people often inflate or add cushioning to their time estimates
B) PERT/CPM was developed in the 1950s so it is too old to be of any use
C) Precedence Diagramming only considers the critical path of a project
D) all of these
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
48
Define predecessor, successor, and parallel activities.Give a real world example of each.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
49
Scheduling other projects so that resources may be shared is_____
A) Critical Chain Project Management
B) Precedence Diagramming
C) PERT
D) Theory of Constraints
E) Critical Path Analysis
A) Critical Chain Project Management
B) Precedence Diagramming
C) PERT
D) Theory of Constraints
E) Critical Path Analysis
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
50
Rent, utilities, insurance and administrative costs are examples of:
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
51
Under the Precedence Diagramming Method, the least common relationship between two activities which occurs when they must complete at the same time is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
52
The cost of labor for using a resource are _____
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
53
The final step in determining the cost of an activity is:
A) determine necessary resources.
B) determining resource quantity
C) determining the cost of each resource
D) ensuring resources are leveled
E) none of these
A) determine necessary resources.
B) determining resource quantity
C) determining the cost of each resource
D) ensuring resources are leveled
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
54
Installing the operating system on a computer before loading any application packages is an example of:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
55
Many organizations have a kick-off meeting because
A) It brings closure to the planning phase of the project
B) It signals the initiation of the next phase of the IT project methodology
C) It communicates to everyone what the project is about
D) It can energize the stakeholders and get everyone excited about working on the project
E) All of these
A) It brings closure to the planning phase of the project
B) It signals the initiation of the next phase of the IT project methodology
C) It communicates to everyone what the project is about
D) It can energize the stakeholders and get everyone excited about working on the project
E) All of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
56
To make a decision to attempt to build an application system based on what was left after a previous attempt ended in failure primarily because of the large investment the company made in the failed project most likely was made by a manager who did not fully understand:
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
57
Under the Precedence Diagramming Method, the situation which occurs when task A cannot end until task B starts is called:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
58
Funds allocated for unexpected expenses are _____
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
59
The idea that there is a cost associated with using a resource is _____
A) Prorated Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
A) Prorated Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
60
_____is ensuring that project resources are not overallocated.
A) Resource leveling
B) Resource constraining
C) Resource starving
D) Resource management
E) Resource addition
A) Resource leveling
B) Resource constraining
C) Resource starving
D) Resource management
E) Resource addition
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
61
When does the project manager or team have the authority to begin executing the project plan?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
62
Why do many people inflate their estimates?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
63
What are the benefits and disadvantages of using Gantt charts as a project management tool?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
64
What is meant by slack (or float)?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
65
What is a kick-off meeting? What purpose does it serve?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
66
Construct an Activity on the Node (AON) network diagram with at least 5 tasks that illustrate predecessors, successors and parallel activities.Label the nodes appropriately and assuming your tasks show estimated durations in days, state the estimated time for completing your project.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
67
Describe the steps necessary for estimating the cost of a particular activity or task that has an estimated duration.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
68
In what ways are project network diagrams similar to Gantt charts and what additional strengths do they have?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
69
Three team members are given the task of estimating activity durations.Mr.Optimist estimates the activity to take 2 days to complete.Ms.Pessimist estimates the activity to take 5 days.Mrs.Realist claims that the most likely estimate is 4 days.What should their PERT analysis assign as an expected duration for the activity and what are the benefits and implications of deploying this tool?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
70
In the context of critical chain project management, what is resource contention?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
71
What is the difference between crashing and fast tracking a project's schedule?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
72
How can parallel activities help shorten the project schedule? Are there any trade-offs?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
73
Define the following and give a real world example of each (other than the ones described in this book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
74
How does the work breakdown structure (WBS) link the project's scope to the schedule and budget?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
75
Why should the project manager ensure that the project resources are leveled?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
76
Assume the following activities for a project along with their estimated durations and predecessors.Describe how critical path analysis would be applied to this project, and calculate the critical path.Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?


Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
77
What is a baseline plan?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
78
What does prorating the cost of a resource mean?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
79
Why should assumptions used in estimating be documented?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
80
What is the critical chain? How is it different from the concept of a critical path?
Unlock Deck
Unlock for access to all 84 flashcards in this deck.
Unlock Deck
k this deck
