A Project Consists of Five Activities AConstruct the PERT/CPM Network for This Problem

Question 1

Essay

A project consists of five activities.Naturally the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing.
​
 Activity  Optimistic  Time (hr)  Most Probable  Time (hr)  Pessimistic  Time (hr)  Floor sanding 345 Floor buffing 123 Paint mixing 0.511.5 Wall painting 129 Ceiling painting 15.57\begin{array} { l c c c } \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time (hr) }\end{array} & \begin{array} { c } \text { Most Probable } \\\text { Time (hr) }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time (hr) }\end{array} \\\hline \text { Floor sanding } & 3 & 4 & 5 \\\text { Floor buffing } & 1 & 2 & 3 \\\text { Paint mixing } & 0.5 & 1 & 1.5 \\\text { Wall painting } & 1 & 2 & 9 \\\text { Ceiling painting } & 1 & 5.5 & 7\end{array}
a.Construct the PERT/CPM network for this problem.
b.What is the expected completion time of this project?
c.What is the probability that the project can be completed within 9 hr.?

Correct Answer:

verifed

Verified

Related Questions