Question 1
Multiple Choice
Effective use of MRP and other dependent demand models does not require which of the following?
Question 2
Multiple Choice
What is the process of tracing upward in the bill of material from the component to the parent item in order to determine the cause for the component requirement?
Question 3
Essay
________ are a way of allowing a segment of the master schedule to be designated as "not to be rescheduled."
Question 4
True/False
Time fences divide that segment of the master schedule that can be revised from that section that is "not to be rescheduled."
Question 5
True/False
Planning bills of material are bills of material for "kits" of inexpensive items such as washers,nuts,and bolts.
Question 6
Essay
Consider the following requirements for a certain product.
Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a.Develop the lot-for-lot MRP table. b.Calculate the total relevant costs.
Question 7
Essay
Explain the difference between a gross requirements plan and a net requirements plan.
Question 8
Multiple Choice
It is week 1 and there are currently 20 As in stock.We need 300 As at the start of week 5.If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week,when and how large of an order should be placed to meet the requirement of 300 As?
Question 9
Multiple Choice
An order for 110 units of Product M has been placed.There are currently 30 units of Product M on hand.Each M requires 4 units of Component N.There are 20 units of N on hand.What are the net requirements for N?