Robin Construction Company began a long-term contract in 2017. The contract price was $800,000. The estimated cost of the contract at the time it was begun was $500,000. The actual cost incurred in 2017 was $350,000. The contract was completed in 2018 and the cost incurred that year was $125,000. Under the percentage of completion method:


A) Robin should report $300,000 of income in 2017.
B) Robin should report $90,000 of income in 2018.
C) Robin will receive interest (under the lookback method) on the underpayment of taxes in 2017.
D) Robin should report $325,000 of income in 2017.
E) None of the above is correct.