Essay
With the backyard poultry craze unleashing a tidal wave of municipal code proposals, Chickenverks is poised to capitalize on the sudden demand for chicken tractors. The portable henhouses they have designed can be assembled in 10 basic steps, each with a required time and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 40 units per hour.
Balance the line according to the longest operation rule and calculate the percent idle time. Using the same arrangement of tasks at work stations, what is the greatest output that can be achieved in an eight-hour day and what is the percent idle time of this design?
Correct Answer:

Verified
The takt time is 60 ∗ 60/40 = 90 seconds...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q58: In stark contrast to a product layout,
Q59: The greater the emphasis on intangible activities,
Q60: A manager deciding where six departments could
Q61: Name a service business that relies heavily
Q62: What are the four levels of customization
Q64: A job shop manufacturing process is better
Q65: What is the optimal location for
Q66: Use this scenario for the following
Q67: The process design team at a
Q68: The table depicts a production line