Multiple Choice
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time and predecessor as shown in the table. They work a 7 hour day and want to produce at a rate of 360 units per day. What should their takt time be?
A) 70 seconds
B) 65 seconds
C) 52 seconds
D) 25 seconds
Correct Answer:

Verified
Correct Answer:
Verified