In an NPV calculation,the final cash flow is typically the:
A) final payment on the investment in the assets used in the project.
B) proceeds from the sale of the last products produced by the project.
C) salvage value obtained by the firm by selling the remaining assets of the project.
D) tax credits that the firm earns through the investment in the project.