Question 21
Essay
According to the PMBOK Guide,the project procurement management knowledge area includes four processes.Identify and briefly describe each of these processes.
Question 22
Multiple Choice
Often a project team will start the selection process by establishing a list of potential suppliers.All of the following information sources are frequently used to identify these potential suppliers EXCEPT:
Question 23
Essay
Compare and contrast traditional project procurement management with the more contemporary approach - project partnering.What are the conditions or sharing requirements for effective project partnerships?
Question 24
True/False
During procurement planning,the project team determines which needs can best be met by acquiring products and services from an outside provider,and which can be accomplished by the team.
Question 25
True/False
The evaluation criteria developed during procurement planning should guide the vendor evaluation and selection.
Question 26
True/False
In many cases,the proposal prepared by the vendor becomes a part of the final contract.
Question 27
True/False
Lean purchasing refers to a manufacturing context where just-in-time (JIT)tools are used to ensure that every step in the supply process adds value,while costs are kept to a minimum.
Question 28
True/False
Among the disadvantages associated with outsourcing is the gradual loss of special skills for doing some specific activities that have been outsourced.
Question 29
True/False
Logistics is the work required to move and position inventory throughout a supply chain.
Question 30
True/False
A project organization can serve as either the buyer or the seller in a project related contract.
Question 31
True/False
Effective project partnerships generally require shared responsibilities,shared resources,shared information,shared rights and shared risks between suppliers and customers.
Question 32
True/False
Supply chains use a combination of modes of transportation including: air,rail,water,pipeline and truck.
Question 33
Multiple Choice
All of the following items are generally considered when selecting the right type of contract EXCEPT:
Question 34
True/False
Extensive supplier evaluation approaches such as surveys,facility visits and financial analysis should be applied to first-tier suppliers only.
Question 35
True/False
On complex projects,despite the importance of factors such as technical capability,managerial capability and previous experience; the selection decision is made mostly or entirely on price.
Question 36
True/False
Supply chain operations require managerial processes that span across functional areas within individual organizations,and link trading partners and customers across organizational boundaries.
Question 37
Essay
Contract types are often associated with two broad categories: fixed-price contracts and cost-reimbursable contracts.Briefly identify the factors to consider when determining which type is most appropriate for a planned contract.