Multiple Choice
There are many causes of variation in project costs.Which of the following accurately describes the nature of this variation?
A) Variation is generally greater on projects that use well-known technology and an experienced project team.
B) Variation occurs in all work processes and the novelty associated with most projects creates many opportunities for variation.
C) Special cause variation comes from many small causes that are inherent in a work process.
D) Special cause variation is when something ordinary occurs
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Which estimating technique uses an algorithm to
Q7: A milestone is a typical measuring point
Q8: On small projects,the cost management plan may
Q12: Vendor bid analysis is used to determine
Q22: Early in a project when very little
Q27: Typically,expedited costs are preferred over regular costs.
Q28: Regardless of what method is used to
Q33: Recurring costs tend to occur during project
Q34: Complex projects such as research and development
Q42: Describe several sources of uncertainty in estimating