Multiple Choice
Which estimating technique uses an algorithm to calculate cost or duration based on historical data and other project parameters?
A) empirical estimating
B) parametric estimating
C) grass roots estimating
D) analogous estimating
Correct Answer:

Verified
Correct Answer: