Project network logic errors include which of the following?


A) Activities with less than 1 day duration
B) Sequences such as "if test successful build prototype, if failure redesign"
C) A sequence such as B succeeds A, C succeeds B, A succeeds C
D) Both B and C are network logic errors
E) A, B, and C are all network logic errors