Multiple Choice
Which of the following is not one of the basic rules to follow when developing project networks?
A) An activity cannot begin until all preceding activities have been completed
B) Each activity must have a unique identification number
C) Conditional statements are allowed but looping statements are not allowed
D) An activity identification number must be larger that that of any preceding activities
E) Networks flow from left to right