Exam 35: Flexibility
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 1
Multiple Choice
The option to increase scope,such as A hotel designed so that the owner can easily diversify beyond lodging services,such as by adding conference facilities,is most similar to:
Question 2
Multiple Choice
In the event tree used in the binomial approach to option valuation,at each node the value either increases or decreases by the proportion u or d,respectively.If the annualized volatility of the underlying asset's value is 10 percent per year and the horizon is six months,what are the up-movement u and down-movement d values?
Question 3
True/False
Managing flexibility depends on manager's ability to recognize,structure,and manage opportunities to create value from operating and strategic flexibility.
Question 4
Multiple Choice
A project has a 50/50 chance of generating either a positive cash flow of $1 per year forever or a zero cash flow.The discount rate is 5 percent.If the initial cost is $10,what is the NPV with the option to stop after the first year?
Question 5
True/False
A project's contingent net present value (NPV )will always be greater than or equal to its standard NPV.
Question 6
Multiple Choice
Which of the following most accurately lists the steps in the four-step process for valuing flexibility in the correct order?
Question 7
Essay
List the three approaches that managers can take when flexibility is neither expected nor required to value assets or projects and the level of uncertainty under which each works best.
Question 8
True/False
Construction of a replicating portfolio can be used to value an option embedded in an investment opportunity.
Question 9
Essay
List the two contingent valuation approaches.Identify which one is more sophisticated and explain when the less sophisticated approach might be preferred.
Question 10
Multiple Choice
The value of flexibility is lowest when:
Question 11
True/False
The value of flexibility is greatest when uncertainty is high and managers can react to new information.
Question 12
Multiple Choice
Which of the following is most accurate concerning how a change in interest rates can produce an increase in the value of a project with flexibility?
Question 13
Multiple Choice
Phased investments,such as a factory that can be built in stages where each stage is contingent on those that precede it and where,at each decision point,management can continue the project by investing additional funds (an exercise price ) or abandon it for some estimated value,would best be categorized as:
Question 14
Multiple Choice
The option to defer investment,such as the ability of a leaseholder of an undeveloped oil reserve to defer development and investment until oil prices have elevated the value of the reserves above their development costs,is most similar to: