What Is the Cost Variance of Project Makeready Based on the Data

Question 107

Multiple Choice

What is the cost variance of Project Makeready based on the data in the earned value table shown below?  Activity 7142128354249 Plan %/1 Complete  Install fixtures 325250575100% Refinish floors 55085635100% Replace doors 350275625100% Completetiling 1,2005651,76580% Install back door 8752251,10070% Landscaping 20035055025% Monthly Plan 3258004351,4751,4404253505,250 Monthly Act 5505505501,1001,6505501,100\begin{array} { | l | l | l | l | l | l | l | l | l | l | } \hline \text { Activity } & 7 & 14 & 21 & 28 & 35 & 42 & 49 & \text { Plan } & \% / 1 \text { Complete } \\\hline \text { Install fixtures } & 325 & 250 & & & & & & 575 & 100 \% \\\hline \text { Refinish floors } & & 550 & 85 & & & & & 635 & 100 \% \\\hline \text { Replace doors } & & & 350 & 275 & & & & 625 & 100 \% \\\hline \text { Completetiling } & & & & 1,200 & 565 & & & 1,765 & 80 \% \\\hline \text { Install back door } & & & & & 875 & 225 & & 1,100&70 \% \\\hline \text { Landscaping } & & & & & & 200 & 350 & 550 & 25 \% \\\hline \text { Monthly Plan } & 325 & 800 & 435 & 1,475 & 1,440 & 425 & 350 & 5,250 & \\\hline \text { Monthly Act } & 550 & 550 & 550 & 1,100 & 1,650 & 550 & 1,100 & & \\\hline\end{array}


A) -$1,896
B) -$1,096
C) -$800
D) -$406

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions