Question 41
True/False
A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.
Question 42
Multiple Choice
A seven activity project has the activity durations (in weeks) and costs shown in the table.The project manager has an overall budget of $20,000,what is the fastest completion time possible?
Question 43
Multiple Choice
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following questions.
-Refer to the scenario above.Suppose the duration of only one activity could be halved.Which activity should be halved to have the greatest impact on project completion time?
Question 44
Essay
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.You have been given a budget of $2,500 and instructed to complete the project as quickly as you can using that amount.Which activities do you expedite and what is the final cost of crashing and project duration?
Question 45
Multiple Choice
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.What is the cheapest crash cost for the project if the contractor must complete all work in 45 days?
Question 46
Multiple Choice
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following questions.
-Refer to the scenario above.Which of these activities has the least slack?
Question 47
Multiple Choice
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following questions.
-Refer to the scenario above.What is the duration of activity H?
Question 48
True/False
Most project management software represents a project in AON format.
Question 49
Essay
A project represented by the activities shown in this table must meet a deadline of 51 days.Sketch the network and determine the critical path.Using the crash costs and minimum activity lengths shown in the table,determine which activities to shorten and provide the total cost of finishing this project in 51 days.
Question 50
Essay
Given the earliest and latest finish times for each of these activities,what are the activity lengths?
Question 51
True/False
The Guide to the Project Management Body of Knowledge (PMBOK®)is divided into two main parts,the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.