Multiple Choice
Consider the system composed of four processes linked by a conveyor belt.There is no storage between these processes pictured below.Which statement is BEST 
A) The overall system output is 220 units/hr.
B) The process that determines the system's capacity is process 4.
C) If only process 3 experiences 5 minutes of unplanned downtime,the system's overall output is diminished.
D) Overall system improvement efforts should focus on process 1.
Correct Answer:

Verified
Correct Answer: