A subdivision is planned for forty houses,each with its own in-ground swimming pool.A contractor estimates it will take him 30 hours to build the first pool and that there is a 90% learning curve associated with this process.
-How long will it take to build all of the pools?
A) 17.1 hours
B) 642.75
C) 796.3 hours
D) 1200.0 hours