Multiple Choice
Your school is considering what to do with the current athletic complex. They plan to either invest in the current athletic complex by upgrading or will invest by building a new one closer to the school's campus. What kind of projects are these?
A) contingent projects
B) mutually exclusive projects
C) independent projects
D) none of the above