Which of the following statements correctly describes a construction cost estimate?
A) Approximation of the probable quantity and unit cost of each element in a project
B) Includes a factor to account for uncertainty and risk associated with project elements and project environment
C) Aggregation of many elements; not a single number
D) All of the above
Correct Answer: