Multiple Choice
A 1 cubic meter (m3) highway embankment will be constructed from soil compacted to a dry unit weight of 17.5 kN/m3. Soil will be trucked to the site from a borrow pit. The natural water content of the soil in the borrow pit is 5% and the bulk unit weight is 17 kN/m3. What is the volume of soil needed from the borrow pit?
A) 12.22 m3
B) 1.08 m3
C) 3.57 m3
D) 10.00 m3
Correct Answer:

Verified
Correct Answer: