Risk in a revenue-producing project can best be adjusted for by:


A) ignoring it.
B) adjusting the discount rate upward for increasing risk.
C) adjusting the discount rate downward for increasing risk.
D) Picking a risk factor equal to the average discount rate.
E) reducing the NPV by 10 percent for risky projects.