Multiple Choice
Based on the following, which event should you be most concerned about? Risk Event
Likelihood
Impact
Bad weather
2
3
Design flaw
3
5
Accident
1
5
Shipment delay
2
2
Power outage
1
5
A) Bad weather
B) Design flaw
C) Accident
D) Shipment delay
E) Power outage
Correct Answer: