Multiple Choice
One common mistake made early in the risk identification process is to
A) Not consider all possibilities.
B) Encourage participants be over optimistic.
C) Support participants being over pessimistic.
D) Focus on consequences and not on the events that could produce consequences.
E) Give too much attention to past events.
Correct Answer: