Question 41
Multiple Choice
A large multinational corporation wants to implement SDN for rapid deployment of application environments. You are asked to define SDN service chaining for a presentation to execute management. In this scenario, which statement would satisfy the requirement?
Question 42
Multiple Choice
You need a security management solution for your data center that will support centralized network visibility and control, J-Flow collection from existing perimeter devices, and SIEM. In this scenario, which two products should you choose for your data center design? (Choose two.)
Question 43
Multiple Choice
Which two statements describe the Contrail vRouter? (Choose two.)
Question 44
Multiple Choice
Click the Exhibit button. Referring to the exhibit, you want the vSRX device to inspect inter-VM traffic. Which two actions must you take to accomplish this task? (Choose two.)
Question 45
Multiple Choice
What are two requirements for a VXLAN tunnel endpoint (VTEP) ? (Choose two.)
Question 46
Multiple Choice
You are designing an IP fabric using EVPN with VXLAN and must ensure that all links between the leaf and spine nodes are used as efficiently as possible. Which two design considerations are important to achieve this task? (Choose two.)
Question 47
Multiple Choice
Which two statements describe the Contrail vRouter? (Choose two.)
Question 48
Multiple Choice
Which two statements about data center design are correct? (Choose two.)
Question 49
Multiple Choice
You are re-designing a traditional multitiered data center into a modern spine-and-leaf data center architecture. In this scenario, which two tiers are collapsed? (Choose two.)
Question 50
Multiple Choice
You have included in your data center design an SRX1500 chassis cluster. The RFP requires a documented upgrade process for the cluster that minimizes downtime. What satisfies this requirement in this scenario?