Multiple Choice
A business analyst working on a project has identified: 3 requirements for which there is a workaround and the users can live without; 2 requirements that the users can live without for now; 15 requirements which, if not delivered, will make the solution unworkable or useless. When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
A) M
B) S
C) C
D) W
Correct Answer:

Verified
Correct Answer:
Verified