A business analyst has interviewed project stakeholders and has a robust list of requirements. At which stages in the requirements engineering framework would he check that these requirements support the business objectives defined at the start of the project?
A) Analysis and validation
B) Elicitation and analysis
C) Elicitation and documentation
D) Validation and documentation
Correct Answer:

Verified
Correct Answer: