Multiple Choice
An issue is showing the Time Tracking section as follows:
There is clearly an hour's difference between the Original and Remaining estimates. Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)
A) Time tracking was not enabled when the work was logged.
B) The remaining estimate was adjusted without logging any effort.
C) The hour's work was logged via a REST call by the user.
D) The work log would have exceeded the project's time allowance, so it cannot be counted.
E) The original estimate was increased.
F) You do not have view permission to see the logged work.
Correct Answer:

Verified
Correct Answer:
Verified
Q29: You have planned, tested, and performed a
Q30: Your project has three issue types that
Q31: Beehive Bank wants to implement Jira with
Q32: Jan asked you to create a new
Q33: A project lead wants to conduct historical
Q35: You are prompted to perform a re-index
Q36: In your organization, a cobbler leads a
Q37: Some of your project owners would like
Q38: You inherited a mature Jira instance with
Q39: Contractors will begin using your Jira instance.